Construction activities include contractor mobilization, initial site preparation, and other related work. Construction crews will enter the site using two access points. The access point for compartment 1A will be located near Cypresswood Drive. The access point for compartment 2 will be located near T.C. Jester Boulevard, just south of Cypress Creek.
About This Project
In total, compartments 1A and 2 of the T.C. Jester Stormwater Detention Basin are expected to provide approximately 210 acre-feet of stormwater storage capacity — that is roughly the equivalent of 210 football fields covered in one foot of water.
A stormwater detention basin temporarily holds stormwater during heavy rain events to help reduce the risk of flooding in the area.
The T.C. Jester Stormwater Detention Basin project is expected to consist of four compartments: one on the west side of T.C. Jester Boulevard and three on the east side (1A, 1B, and 2). Construction on compartment 1B is in progress and anticipated to be completed in Q2 2027. Construction on the west compartment is anticipated to begin in Q2 2027.
Funding
The Flood Control District expects to contribute up to $3.3 million, including $600,000 from the 2018 Bond Program.
- In addition, compartments 1A and 2 are expected to receive up to
- $9.9 million in federal Community Project Funding secured by Congressman Dan Crenshaw through the Federal Emergency Management Agency.
- The construction contract was awarded for $9.5 million.
Project Location
The project is located just north of Cypress Creek at T.C. Jester Boulevard and Cypresswood Drive.
Anticipated Schedule
- Construction Start: Q4 2026
- Construction Completion: Q2 2027
The Flood Control District appreciates the support of federal, state, and local partners as the implementation of flood risk reduction projects continues across the Cypress Creek watershed.